The D. Maria II Theatre's Workshop Conversion Overshoots Its Contract by 3.76 Million Euros and 575 Days, the Procurement Portal Shows

Turning the old set-building area of Lisbon's national theatre into workspaces cost 12.3 million euros against a contract price of 8.57 million, 43.9 percent more, after seven rounds of extra works and three deadline extensions.

The D. Maria II Theatre's Workshop Conversion Overshoots Its Contract by 3.76 Million Euros and 575 Days, the Procurement Portal Shows
The Teatro Nacional D. Maria II on the Rossio, Lisbon, in an archive photo taken before the works. Photo: Michael Gaylard, Wikimedia Commons, CC BY 2.0

The works to turn the old set-building area of the Teatro Nacional D. Maria II (D. Maria II National Theatre) in Lisbon into workspaces cost 12.3 million euros, against a contract price of 8.57 million euros. The difference is 3.76 million euros, or 43.9 percent more than agreed. The works also took 575 days longer than planned.

The figures come from the contract's closing record on the Portal BASE (the public procurement portal), where the theatre has now filed the final account. The business news site ECO reported the overrun on Thursday.

The contract

  • The work: "Reconversão da área de cenografia em espaços de trabalho" (conversion of the set-design area into workspaces) at the theatre on the Rossio, Praça D. Pedro IV.
  • The builder: CARI Construtores, S.A., chosen in a concurso público (open tender) that drew seven bidders.
  • Signed: 13 January 2023, for 8,566,623.38 euros, with a deadline of 487 days.
  • Final cost: 12,323,172.19 euros, recorded as the "total effective price".
  • Closed: 3 November 2026, recorded as full performance of the contract.

Why it cost more

The closing record gives four reasons for the higher price:

  • seven sets of complementary works, labelled MC01 to MC07;
  • the removal of some planned works that were not carried out, which pulled the other way;
  • the final ordinary price revision, the indexation of a building contract's prices to changes in costs over the life of the job;
  • three "reposições do equilíbrio financeiro" (restorations of the contract's financial balance).

The record refers to a final account attached to an internal report, I08010-202611-DAF. That report is not public on the portal, so the split between the four items is not known.

According to ECO, the documents on the portal attribute the complementary works to errors and omissions in the design, some found only once work had started. ECO lists non-structural demolition on floors -2 and -3, new openings and a slab opening on floor -2, structural reinforcement on floor 4, and the rerouting of a water supply pipe. ECO said it had asked the Ministry of Culture and the builder about the delays and the cost, and was awaiting a reply.

Three extensions

The portal lists three extensions to the original 487-day deadline:

  • 373 days, to 29 October 2025;
  • 122 days, linked to the fifth set of complementary works, to 28 February 2026;
  • 80 days, linked to the seventh set, to 19 May 2026.

That adds up to 575 extra days. The theatre took provisional delivery of the work on 29 May 2026.

Part of a larger refurbishment

The contract ran alongside the requalification that kept the national theatre's building on the Rossio closed from 2023. When the building reopened to the public on 18 September, the theatre's board put the whole investment at 15.1 million euros, funded through the Plano de Recuperação e Resiliência (PRR, the Recovery and Resilience Plan). On the eve of the reopening, the workers' committee complained about unfinished working conditions inside the building; the board said the issues had been resolved.

The theatre is a public business entity (an EPE) under the Ministry of Culture. Its contracts, and their closing records, are published on the Portal BASE, where anyone can read them.