Sesimbra, Seixal and Palmela Rally at a Roundabout Over National Roads, as the 20 Million Euro EN 378 Overhaul Is Pushed Back to 2027
Three Setúbal peninsula mayors protested together on Tuesday over the EN 377, 378 and 379. The EN 378 overhaul, contracted in May and due to start in September, has been pushed back to 2027, after the winter.
The mayors of Sesimbra, Seixal and Palmela stood together at the Marco do Grilo roundabout on Tuesday afternoon to demand urgent repairs to three national roads on the Setúbal peninsula: the EN 377, the EN 378 and the EN 379. All three belong to the state road company, Infraestruturas de Portugal (IP), not to the councils, and the mayors say promised works keep slipping while drivers face a second winter on broken, flood-prone surfaces.
The protest, held on the border between Fernão Ferro (Seixal) and Castelo (Sesimbra), brought together mayors, councillors and parish council presidents from several parties and residents, Lusa reported via Notícias ao Minuto.
The EN 378: from a September start to 2027
The EN 378 links Seixal and Sesimbra. In December 2025, after storm Cláudia, IP said the road's condition had worsened significantly, carried out emergency cleaning and cold-asphalt patching between km 5.2 and km 10.8, and promised a structural overhaul worth an estimated 20 million euros, with drainage rebuilt in full, a tender in early 2026 and works starting by the end of June 2026.
On 15 May 2026 IP announced it had awarded the contract for about 10.7 km between Seixal and Fernão Ferro, covering paving, drainage, new and redesigned roundabouts, traffic lights to control speed, signalled pedestrian crossings and relocated bus stops. The same release said a flood sensor at km 5.5 in Fernão Ferro had triggered two preventive closures of the road in February, lasting 3 hours 54 minutes and 3 hours 12 minutes.
The works have not started. In a statement on 18 November, Seixal council said the initial plan was to begin in September and that the intervention has since been pushed back to 2027, after the winter. Sesimbra's mayor, Francisco Jesus, said the tender for the next stretch, from Marco do Grilo to Santana, had been due in the first half of 2026, and that there are now too many potholes to fill one by one, so stopgap works are needed before winter. Seixal's mayor, Paulo Silva, recalled repeated flooding on the road last winter.
Palmela: the EN 379 and EN 252
Palmela's mayor, Ana Teresa Vicente, said the EN 379 and the EN 252 have been promised works for 2027 and 2028, after earlier promises for 2025 and 2026. In a council notice on 23 November, Palmela said IP had told it that a resurfacing design for the EN 379 had recently been contracted and that a tender to resurface the EN 252 would be launched next year. The council also said IP had received no instruction to study the bypass roads in its municipal master plan, despite a commitment from the infrastructure minister. The EN 379 runs from Palmela through Azeitão to the port of Sesimbra; the EN 377 lies entirely within Sesimbra.
What it means for drivers
- No structural work on the EN 378 is expected before 2027, so expect the current surface, patch repairs and possible flood closures this winter, especially around Fernão Ferro.
- When work does start, the Seixal to Fernão Ferro stretch will be a long building site with new roundabouts and changed junctions.
- IP can close the EN 378 preventively when its flood sensor trips; during heavy rain, check before setting off. This month's storms have already shown how quickly roads can be cut (see our storm Charles coverage).
IP's record on contract delivery was already under scrutiny: earlier this month the Court of Auditors found that almost half of 676 million euros of extra works on public contracts from 2023 to 2025 was at IP.