Lisbon's Eastern Hospital Will Cost the State Up to 898.9 Million Euros, 23 Percent Above Its 2024 Ceiling, and Open on 1 December 2029

Cabinet raises the ceiling on the Hospital de Lisboa Oriental partnership from 732.3 million euros after the EU recovery money was withdrawn, and sets an opening date later than the 2027 planned in 2024. Six central Lisbon hospitals wait to move.

Lisbon's Eastern Hospital Will Cost the State Up to 898.9 Million Euros, 23 Percent Above Its 2024 Ceiling, and Open on 1 December 2029
São José hospital, one of the six the new hospital replaces. Photo: José Luiz, CC BY-SA 3.0, via Wikimedia Commons

The Council of Ministers on Thursday 19 November raised the ceiling on what the State may pay for the Hospital de Lisboa Oriental (Lisbon Eastern Hospital), the public-private partnership (PPP) that is to replace six of central Lisbon's oldest hospitals, to 898.9 million euros plus VAT at current prices. The same resolution fixes 1 December 2029 as the date the new hospital opens, according to the Council of Ministers communiqué. The revision, the Government says, "guarantees the continuity and financing of the project after the withdrawal of the PRR funds", the money Portugal draws from the EU's Recovery and Resilience Plan.

What has changed since 2024

The last authorisation, Resolução do Conselho de Ministros n.º 22-A/2024 (Council of Ministers Resolution 22-A/2024) of 1 February 2024, set two figures:

  • The PPP payments: up to 732.3 million euros plus VAT at current prices, paid yearly from the hospital's opening, then "planned for 2027", to 2053. The new ceiling is 166.6 million euros, or about 23 percent, above it.
  • The EU money: up to 100 million euros plus VAT more from the PRR, to be spent from 2024 to 2026 on building the western tower and two other buildings on the site. Under the tender rules, that grant was to reduce the State's later payments to the operator.

Thursday's communiqué gives neither the new yearly payments nor a breakdown of the 898.9 million euros, and it does not say how much of the increase replaces the lost PRR money and how much comes from inflation or the later opening. The resolution itself has not yet appeared in the Diário da República (the official gazette).

The hospital

The tender for the PPP was launched in December 2017 and the contract was awarded only on 18 July 2022, with a bid 23 percent below the base price, the 2024 resolution records. According to ECO's account of the contract, signed in February 2024:

  • the hospital has been a priority since 2008;
  • it is to have three buildings and 875 beds on a 180,000 square metre site in Marvila, in eastern Lisbon;
  • it replaces São José, Santa Marta, Santo António dos Capuchos, Dona Estefânia, Curry Cabral and the Maternidade Alfredo da Costa maternity hospital, today part of the Unidade Local de Saúde (ULS, Local Health Unit) de São José;
  • the consortium is led by Mota-Engil, and the PPP runs for 30 years: three to build it and 27 to maintain it;
  • unlike Portugal's earlier hospital PPPs, the private partner does not run the clinical side, which stays with the Serviço Nacional de Saúde (SNS, the national health service).

The PRR money was lost in April, when the Government also set up a commission to renegotiate the contract with the consortium. In June the Tribunal de Contas (Court of Auditors) rejected a minister's claim that its review of the contract had delayed the hospital and added to its cost.

Until it opens, the six old hospitals carry on. This month São José opened a 30-bed unit for emergency patients waiting for a ward. The Health Minister last month promised another wave of hospital PPPs, and the Government has ordered a study of a building-only PPP for Barcelos and Esposende on the same model.