Lisbon Metro's Violet Line to Loures Stalls Again Until Brussels Sees the Contract With a Third Train Supplier
The 677.5 million euro light rail line between Loures and Odivelas still has no construction contract. Brussels is waiting for the Mota-Engil consortium's deal with a third rolling-stock supplier, and the line could go to the runner-up.
The Violet Line, the light rail route the Lisbon Metro is to build between Loures and Odivelas, is stuck again. The construction contract has still not been awarded, and the European Commission is waiting for the winning consortium to hand over its contract with a new supplier for the line's trams, ECO reported today. The consortium led by the builder Mota-Engil has named a third rolling-stock supplier, according to ECO, which puts the investment at 677.5 million euros.
ECO also reports that the Commission has said Metropolitano de Lisboa, the state-owned company that runs the metro, may hand the line to the second-placed bidder in the tender if the Mota-Engil consortium does not meet the commitments it made to Brussels.
How the line got here
Metropolitano de Lisboa launched the tender in April 2025 for the design, construction and maintenance of the new line. In November 2025 the Commission opened an in-depth investigation under the Foreign Subsidies Regulation, the EU law that polices state support given to non-EU companies bidding in European tenders. Its target was Portugal CRRC Tangshan Rolling Stock, the Portuguese arm of the Chinese state-owned train maker CRRC, which was the consortium's subcontractor for the light rail vehicles.
On 21 April 2026 Brussels cleared the metro to award the contract, on condition that the consortium kept to its commitments. The consortium, made up of Mota-Engil, Zagope and Spie Batignolles, had swapped CRRC for the Polish manufacturer PESA, Observador reported. The Commission stressed that the final decision on the award lies with the metro company, which must check that the revised bid still meets the tender's technical and quality rules.
In July, ECO reported that PESA had also pulled out. The tender jury cannot approve the award until a supplier is named for the line's 12 light rail vehicles, which will serve 17 stations between Odivelas and Loures. The winning bid was 598.9 million euros, according to the same report.
What it means for Loures and Odivelas
- No start date yet. With no contract signed, building work cannot begin, and ECO's report gives no new date for the line.
- EU recovery money is already gone. ECO reported in July that the Violet Line, like the Red Line extension, was dropped from Portugal's Recovery and Resilience Plan (PRR) because of the delays, so it now has to be paid for from other sources.
- A further delay is possible. If the Commission's conditions are not met, the contract could go to another bidder, and ECO's July report noted that losing bidders could challenge the change of supplier.
The Infrastructure Minister, Miguel Pinto Luz, told parliament on 7 April that the line would go ahead whatever Brussels decided, ECO reported. The metro's other big expansion, the Red Line to Alcântara, needed a new financing decision in October before its works could move.