Iberdrola Abandons Its 426 Million Euro Green Ammonia Plan for Sines, as an AI Data Centre Campus Joins the Industrial Zone
The zone's manager confirmed the Spanish utility's exit to Expresso. The project would have made about 95,000 tonnes of ammonia a year from 2027. Fortitude Capital is developing a 202 megawatt data centre campus nearby.
Iberdrola has given up its plan to make green ammonia at Sines. The project was budgeted at 426 million euros and had been granted national-interest status. AICEP Global Parques, the State company that manages the Zona Industrial e Logística de Sines (Sines Industrial and Logistics Zone, ZILS), confirmed the withdrawal to Expresso, ECO reported on Monday. Neither report gives a reason, and Iberdrola has not made a public statement.
In the same update, the zone's manager announced a new arrival: a 202 megawatt data centre campus for artificial intelligence, being developed by the Lisbon investment firm Fortitude Capital.
What Sines loses
The Spanish utility called the project Green Ammonia Express Sines. Its scoping file with the Agência Portuguesa do Ambiente (Portuguese Environment Agency, APA), put out to public consultation in January 2024, describes the plan in detail:
- 137 megawatts of electrolysers making green hydrogen on site, turned into about 95,000 tonnes of green ammonia a year;
- about 21 hectares inside the industrial zone, powered by a dedicated renewable park of about 220 megawatts;
- a pipeline to carry the liquefied ammonia to the Port of Sines for export by sea;
- an investment of 426.8 million euros, 55 direct jobs, and operation from December 2027.
The environmental evaluation committee's opinion of 2024 records two things. The government's investor-support committee had classed the project as being of potential national interest (PIN), a status that speeds up licensing. And the port authority had refused the storage tanks Iberdrola wanted inside the port. The APA's scoping decision, signed in February 2024, lapses if the full environmental impact assessment does not start within two years. The public record does not show whether that assessment was ever filed.
According to ECO's account of the Expresso report, the plot Iberdrola had reserved sits next to the Swedish company Stegra's planned green steel plant, and AICEP Global Parques counted on 220 indirect jobs as well as the direct ones.
A thinning hydrogen pipeline
Iberdrola's exit adds to a pattern. ECO notes that the roughly 40 green hydrogen projects cleared to proceed in Portugal are fewer than half the number that have been cancelled, refused or allowed to lapse. Sines lost another large consortium project, H2Sines.Rdam, in 2024.
Others are still moving. In October the Comissão de Coordenação e Desenvolvimento Regional do Alentejo (Alentejo Regional Coordination and Development Commission) issued installation permits for the MP2X hydrogen project and the MADOQUA NH3 ammonia project in the same zone. ECO adds that projects from Galp, Repsol and HyChem could start before the end of this year.
What Sines gains
Fortitude Capital, a private equity firm founded in 2022, says on its own website that it is developing the Hermes Data Center, "a 202 MW greenfield AI data center campus" in the zone, designed for "high-density AI and high-performance computing workloads". The firm has published no investment figure, timetable or licence for it, and no environmental assessment has been found.
Data centres are about to face new national rules: the government has ordered the Direção-Geral de Energia e Geologia (Directorate-General for Energy and Geology) to write grid connection rules for them by 11 December.
Sources: APA scoping proposal, evaluation committee opinion and scoping decision for Green Ammonia Express Sines (2024); Fortitude Capital's website; ECO (23 November 2026), reporting AICEP Global Parques's confirmation to Expresso.