Eastern Lisbon's New Hospital Will Not Open Until December 2029, and Its PPP Ceiling Grows to 898.9 Million Euros After It Lost Recovery-Plan Money

A Council of Ministers resolution published on Wednesday rewrites the Hospital de Lisboa Oriental payment plan after 100 million euros of PRR funds were withdrawn, with state payments running to 2054.

Eastern Lisbon's New Hospital Will Not Open Until December 2029, and Its PPP Ceiling Grows to 898.9 Million Euros After It Lost Recovery-Plan Money
The entrance to Hospital de São José in central Lisbon. Illustrative. Photo: Vitor Oliveira, Wikimedia Commons, CC BY-SA 4.0

The new Hospital de Lisboa Oriental (Eastern Lisbon Hospital) will not open before 1 December 2029, and the state's maximum bill for the public-private partnership (PPP) that is building it rises to 898.9 million euros plus VAT, under a Resolução do Conselho de Ministros (Council of Ministers resolution) published in the Diário da República (the official gazette) on Wednesday 25 November.

The resolution, n.º 229/2026, was approved on 19 November. It rewrites the payment plan after the project lost 100 million euros of European money from Portugal's Plano de Recuperação e Resiliência (PRR, the Recovery and Resilience Plan).

Why the money went

The PPP contract to design, build, finance and maintain the hospital was signed on 2 February 2024, and the Tribunal de Contas (Court of Auditors) cleared it on 28 May 2024. A resolution earlier that year had allowed a PRR contribution of up to 100 million euros, which lowered the "availability payments" the state makes to the private partner over the life of the contract.

That allocation was "revoked in full", the resolution says, when the Council of the EU approved Portugal's revised recovery plan on 12 December 2025. When the contribution was approved, the PRR money had to be spent by 30 June 2026, Jornal de Negócios reported in October 2025.

The government then set up a committee in April 2026 to renegotiate the contract with the private partner. The resulting addendum, approved by the secretaries of state for health management and for the Treasury on 11 and 12 November, removes the PRR amounts from the payment plan, resets the works timetable and fixes 1 December 2029 as the date the hospital complex starts operating.

How the bill has grown

The new ceiling is 898,898,528.11 euros at current prices, plus VAT. It includes 23 million euros already paid in 2024 and 1.84 million euros in 2025. The previous ceiling, set in October 2025, was 796.4 million euros, according to Jornal de Negócios, so the cap rises by about 102.5 million euros, or 12.9 percent, by The Portugal Brief's calculation. That is close to the 100 million euros of lost PRR money. The 2024 ceiling was about 732.3 million euros.

The 2025 payment came in well under plan: the October 2025 schedule allowed 6.7 million euros for that year. Under the new schedule, the yearly maximum is 43.1 million euros in 2027, 29.7 million in 2028 and 45.2 million in 2029, peaking at 49.5 million in 2031. Payments run until 2054, when they fall to 11.0 million euros. Each year's amount can be raised by unspent balances from earlier years and is adjusted in line with consumer prices. The money comes from the budget of the Administração Central do Sistema de Saúde (ACSS, the health service's central administration).

Claims settled

The addendum also fixes compensation and extra costs owed to the private partner, but only for additional works linked to delays caused by procedures and administrative steps that were "exclusively" the state's responsibility. In return, the company that manages the building waives every other claim for compensation or more time based on technical or geological surprises, or on the classification of the soil, submitted up to now. The government says this protects the public interest and reduces the risk of future litigation.

What the hospital is for

The hospital is being built in Marvila, in eastern Lisbon, by a consortium led by Mota-Engil. It is meant to replace six older Lisbon hospitals, according to Jornal de Negócios. The project went to tender in December 2017. The health minister promised another wave of hospital PPPs in October.

The resolution does not say what the opening date was before this revision, how much compensation the private partner will receive, or how much of the higher ceiling is due to inflation rather than the lost PRR money.

Source: Resolução do Conselho de Ministros n.º 229/2026, Diário da República n.º 229, Série I, 25 November 2026 (in Portuguese).