Councils Around the Future Girabolhos Dam Are Promised Cheaper Electricity and Better Roads, With No Figures Yet
The environment minister told mayors in Seia that the five councils around the planned Girabolhos reservoir on the Mondego will get an electricity tariff cut and road works. No amount, roads or dates have been set; the dam's tender runs to April 2027.
The councils on the upper Mondego, where the planned Girabolhos dam would flood a stretch of the river valley, have been promised compensation in two forms: a cut in the electricity tariff and better road access. Environment and Energy Minister Maria da Graça Carvalho said so on Friday in Seia, in the Guarda district, but neither the size of the discount nor the roads have been decided yet.
"We are studying the benefits or compensation, which will be a reduction in the electricity tariff, and what the mayors asked us for most was road access," the minister said, according to Lusa, as published by Observador and ECO. She was meeting the region's mayors to report back on what they had asked for during her previous visit on 1 October.
Roads: the mayors must pick
On roads, the minister said that "all roads are extremely expensive" and asked each council to name its priorities. She said she had already met the Secretary of State for Infrastructure, and that she hoped to take the councils' priority list back to Lisbon on Friday. No road, budget or timetable has been announced.
She also said the government has decided to pay the future operator for the energy storage the plant will provide, describing it as a pumped storage scheme (water is pumped uphill when power is cheap and released through turbines when it is needed). That payment needs clearance from Brussels, and she said she would discuss it on Monday, 30 November, with the European Commission's Director-General for Energy. The government expects this to make the tender more attractive to bidders.
Where the dam stands
Girabolhos is not built, and no builder has been chosen. The government launched an international public tender on 15 July in Gouveia, the government's own news release says. The winner gets a 65-year concession to design, build and run the scheme, with a minimum output of 40 megawatts. Bidders have 270 days to submit proposals; Lusa gives the deadline as 9 April 2027, and the minister said several interested parties have asked for clarifications. The winner then has 60 months to deliver the scoping proposal and the environmental impact study.
The Portuguese Environment Agency (APA), which runs the tender, describes a multi-purpose scheme: renewable electricity, water reserves for public supply, and flood control in coordination with the existing Aguieira dam downstream. The reservoir would sit on a stretch of the Mondego in five councils: Seia, Gouveia and Fornos de Algodres in the Guarda district, and Mangualde and Nelas in the Viseu district. The project has been planned since 2007, and the minister ordered the tender in February after floods in the Mondego basin. Last weekend's red rain warning covered the Coimbra, Viseu and Guarda districts.
The scheme has critics. In August the environmental group Zero called for the tender to be suspended, Notícias ao Minuto reported. It argued that the tender documents set no specific flood-control requirements and that an operator paid for electricity has a reason to keep the reservoir as full as possible.
What it means for you
If you live in one of the five councils, nothing changes on your electricity bill yet. The discount is a promise without a figure, a start date or a list of who qualifies. Watch your council for its road priority list, and for the tender result after April 2027.